Finishing
Activities
- Rough plumbing
- Rough heat and
fireplace
- Rough electrical
- Pour basement and garage
floor
- Rough plumbing inspection by
Municipal Building Inspector
- Rough electrical inspection by
Municipal Building Inspector
- Rough frame punch out by
contractors
- Rough frame inspection by
Municipal Building Inspector
- Insulation
- Insulation inspection by
Municipal Building Inspector
- Hang Drywall
- Tape and mud
drywall
- Sand drywall
- Installation of garage
door
- Brick Installation
- Installation of
siding
- Prime interior house for
paint
- Trim, baseboard, closets,
shelves and rails
- Installation of
cabinets
- Install drainfield and set
septic tanks
- Approximately 40 days to
Completion
Click Here For More Finishing Activities |
|
|
|