Construction Process

Finishing Activities
  • Rough plumbing
  • Rough heat and fireplace
  • Rough electrical
  • Pour basement and garage floor
  • Rough plumbing inspection by Municipal Building Inspector
  • Rough electrical inspection by Municipal Building Inspector
  • Rough frame punch out by contractors
  • Rough frame inspection by Municipal Building Inspector
  • Insulation
  • Insulation inspection by Municipal Building Inspector
  • Hang Drywall
  • Tape and mud drywall
  • Sand drywall
  • Installation of garage door
  • Brick Installation
  • Installation of siding
  • Prime interior house for paint
  • Trim, baseboard, closets, shelves and rails
  • Installation of cabinets
  • Install drainfield and set septic tanks
  • Approximately 40 days to Completion